On March 15, the delegation of the Ministry of Transport led by Minister Nguyen Van Thang The leader went to the field to check 2 projects Vinh Hao – Phan Thiet expressway and Phan Thiet – Dau Giay to remove the difficulty of the situation lack of land to fill the foundationspeeding up the time to put into use before April 30, 2023.
Investor’s report says paragraph Phan Thiet – Dau Giay expressway nearly 90% of construction and installation volume, basically in time to put into operation before April 30. Private line Vinh Hao – Phan Thiet expressway Only 75% progress has been achieved, the remaining workload is very large. The biggest problem currently on this highway is the lack of materials backfill soil because 6 specific mines of the project have expired mining license.
At a meeting with the People’s Committee of Binh Thuan province in the afternoon of the same day, Minister Nguyen Van Thang assigned the investor and contractors to closely coordinate with the locality, remove difficulties, and complete the entire main line of the project. The above 2 projects are to be handed over and put into use before April 30, 2023. Regarding the lack of earth filling materials on the Vinh Hao – Phan Thiet expressway, Minister Nguyen Van Thang asked the People’s Committee of Binh Thuan province to make a written request to the Government to consider and allow the People’s Committee of Binh Thuan province to carry out Expired 6 licenses for mining earth embankment to serve the construction of Vinh Hao – Phan Thiet expressway project, instead of being re-issued as prescribed in Resolution 31 of the Government.